To calculate the Planned Value, PV, you just need to add the amount of work that was supposed to be done by 3rd day. Three sides were supposed to be done. The budget to complete each of the three sides was 0. So the planned value, PV, is 500+500+500= 00. But, what is actually done by 3rd day is, two sides completely done and third side is only 50% done, hence the Earned Value, EV is 500+500+250=50 The actual cost, AC, of doing the work is 500+700+300= 00. Now, since we know, PV, EV and ACcalculating CPI and SPI is pretty straight forward. Just put these into the formulas we learn earlier. Do this as an exercise!
Earned Value Problem Solution
About Giribee
Subscribe
Leave a Reply Click here to cancel reply.
Categories
- Andra bank IFSC codes (1)
- Astrology (2)
- Baba Ramdev (31)
- Bangalore bank IFSC codes (861)
- Bank IFSC code (23250)
- Black jack (361)
- cafe world (88)
- cake recipes (107)
- Cars (16)
- chirstmas (1531)
- Contests (4)
- Diwali Deepavali Recipes (1)
- dragon wars (158)
- Facebook games (5625)
- farmville (3726)
- Fashion Wars (622)
- Featured (8)
- Festival Recipes (12)
- fishville (36)
- Free ebooks (4)
- Games (7380)
- Ganesh Chaturthi (11)
- Google Plus Games (66)
- Google+ (2040)
- hairstyles (2)
- Health (50)
- Life In Bangalore (4276)
- Mafia war (2065)
- Mobiles (349)
- Movies (42)
- new year 2010 (237)
- News (18)
- Non Veg (16)
- petville (563)
- Pirates (5750)
- PMP (2497)
- PMP study guide and tips (2)
- Ramzan Recipes (24)
- Recipes (16)
- Roller Coaster (666)
- shewag (1)
- SMS (19)
- Special Forces (125)
- Street Racing (135)
- Technology (4282)
- Travalogue (2)
- vampire wars (400)
- Veg Recipes (9)
- zynga poker (1712)
© 2012 All out Bangalore. All Rights Reserved.
Powered by WordPress. Designed by ![]()

No comments yet.